Vent: the finisher foreman in Amarillo said my mix was too wet for a driveway, and he was dead right
Back in April I was pouring a 24 by 30 driveway outside Amarillo and the foreman, Dale, kept telling me to cut water on the mix. I figured a 4 inch slump was fine in the pan but a 6 inch was way too loose, and I remember him saying "you'll see spider cracks by June." Sure enough, by the middle of June there were hairline cracks all over the east side where the sun hits first. Now I'm tearing out a 10 foot section and eating the cost of 3 yards of concrete out of my own pocket. What slump do you all run for driveways in that kind of heat, and do you add water at the chute or only at the truck?